Overview & Structure
IS 2911 provides the code of practice for the design and construction of pile foundations. It is structured into four parts covering different pile types and testing: Preamble
| Part | Title | Latest Revision |
|---|---|---|
| Part 1 / Sec 1 | Driven Cast-in-Situ Concrete Piles | 2010 |
| Part 1 / Sec 2 | Bored Cast-in-Situ Concrete Piles | 2010 |
| Part 1 / Sec 3 | Precast Concrete Piles | 2010 |
| Part 3 | Under-Reamed Piles | 1980 |
| Part 4 | Load Test on Piles | 2013 |
- Hard strata is at a depth where shallow foundations become uneconomical
- Soil near the surface is weak (soft clay, loose sand, expansive soil)
- Heavy concentrated loads from columns
- Scour depth is deep (bridge foundations in rivers)
- Expansive soils causing heave/shrinkage
Pile Classification
Piles can also be classified by load transfer mechanism:
- End-Bearing Piles: Transfer load through tip to hard stratum below.
- Friction Piles: Transfer load through skin friction along the shaft.
- Compaction Piles: Used to densify loose granular soils.
- Tension Piles: Resist uplift forces (anchor piles).
- Lateral Load Resisting Piles: Resist horizontal forces (retaining walls, dolphins).
Pile Capacity Estimation
The ultimate load capacity of a single pile is the sum of its end-bearing capacity and shaft (skin) friction capacity. Appendix A / Cl. 6
For Cohesive Soils (Clay)
For Granular Soils (Sand/Gravel)
Part 1 / Sec 1: Driven Cast-in-Situ Piles
These are formed by driving a steel casing into the ground, filling it with concrete, and withdrawing the casing. IS 2911 (Part 1/Sec 1)
Construction Sequence
- Position the casing at the pile location using a template or guide.
- Drive the casing using drop hammer, diesel hammer, or vibratory hammer.
- Excavate soil from inside the casing (if necessary for cleaning).
- Pour concrete into the casing (dry pour or tremie method).
- Withdraw the casing gradually while maintaining concrete pressure.
- Install reinforcement cage before or after concreting (as applicable).
Key Specifications
| Parameter | Requirement |
|---|---|
| Diameter | 300 mm to 600 mm (common). Up to 1200 mm for large projects. |
| Length | Typically 6 m to 30 m. Beyond 30 m requires special provisions. |
| Concrete Grade | Minimum M25 for structural piles. |
| Clear Cover | 50 mm (minimum) for above-ground piles; 75 mm in aggressive soils. |
| Minimum Reinforcement | 0.4% of gross cross-sectional area. |
| Spacing of Ties | Not exceeding 300 mm or 12 times main bar diameter. |
Part 1 / Sec 2: Bored Cast-in-Situ Piles
These are formed by boring a hole into the ground and then filling it with concrete. Most widely used in urban construction due to low noise and vibration. IS 2911 (Part 1/Sec 2)
Boring Methods
- Rotary Drilling: Using auger bits with bentonite slurry for stabilization.
- Percussion Drilling: Chisel dropped repeatedly for hard rock / boulder soil.
- Grab / Shell: Cable-operated grabs for soft soils.
Key Construction Checks
Specifications
| Parameter | Requirement |
|---|---|
| Diameter | 450 mm to 1500 mm (common). Up to 3000 mm for bridge foundations. |
| Concrete Grade | Minimum M25 (or M30 in corrosive environments). |
| Slump | 150โ200 mm for tremie concrete. |
| Clear Cover | 75 mm (minimum) in soil; 100 mm in aggressive/marine conditions. |
| Longitudinal Steel | 0.4% to 2.5% of gross area. |
| Transverse Ties | โฅ 8 mm bars at spacing โค 300 mm or half shaft diameter. |
Part 1 / Sec 3: Precast Concrete Piles
Piles manufactured offsite and transported to location for driving. Suitable for marine structures, bridge foundations, and projects requiring large quantities of identical piles. IS 2911 (Part 1/Sec 3)
Advantages
- Quality control in factory conditions
- Fast installation โ no curing time at site
- Can be inspected before driving
- Can be prestressed for higher capacity
Disadvantages
- Difficult to transport long piles
- Cannot adjust length easily after driving
- Requires heavy driving equipment
- Noise and vibration during driving (problematic in urban areas)
Driving Formulae
The pile capacity can be estimated from driving records using dynamic formulae:
Part 4: Load Testing of Piles
Load testing is the most reliable way to determine pile capacity. IS 2911 (Part 4):2013 defines two types: IS 2911 (Part 4)
Types of Load Tests
Maintained Load Test Procedure
- Apply load in increments of 25% of design load.
- Hold each increment until settlement rate falls below 0.1 mm/hour (or 2 hours, whichever is greater).
- Record settlements at the pile head using dial gauges (min 4, at 90ยฐ intervals).
- After reaching maximum test load, hold for 24 hours (or until settlement stabilises).
- Unload in equal decrements. Record rebound at each stage.
Permissible Settlement
| Pile Type | Max Settlement at 1.5ร Working Load |
|---|---|
| Single pile (isolated) | 12 mm |
| Pile group (10+ piles) | 25 mm |
| Bridge foundations | As per IRC provisions |
Group Pile Effects
Piles are rarely used individually. They are arranged in groups with a pile cap. The capacity of a group may differ from the sum of individual pile capacities. Cl. 5.5
Group Efficiency (ฮทg)
Spacing Rules
- Minimum Centre-to-Centre Spacing: 2.5ร pile diameter (friction piles) or 2ร diameter (end-bearing piles).
- Preferred Spacing: 3ร diameter for friction piles to ensure group efficiency โ 1.0.
Lateral Load Capacity
Piles must also resist horizontal forces (wind, seismic, earth pressure). IS 2911 references the IS code for lateral load tests. Appendix B
Methods of Analysis
- IS Code Method: Based on Broms' theory โ assumes soil as elastic continuum and pile as flexible beam.
- p-y Method: More advanced, used in software (LPILE, REPUTE). Defines soil reaction (p) as a function of lateral deflection (y).
- Empirical Approach: Lateral capacity โ 1% to 3% of axial capacity for typical piles in medium dense sand.
Related Codes
Pile design requires coordination with several other codes: